Neat-line and order quantities for pipeline trenching: excavation, bedding, pipe zone, native backfill, spoil haul-off with swell, import tonnage, and truckloads. Runs entirely offline; inputs persist in this browser via localStorage.
Use limits: Neat-line quantities assume a rectangular trench prism at the average dimensions entered. Sloped or benched excavations, potholes, trench boxes over-cut, and appurtenance excavations (manholes, valve clusters, thrust blocks) are on top of these numbers. Pay quantities are per the contract's measurement rules — this tool is for ordering material and scheduling trucks, not for the pay estimate.
Neat-Line Quantities
Excavation (bank)
—
Pipe displacement
—
Bedding
—
Pipe zone (net of pipe)
—
Backfill above pipe zone
—
Order & Haul Quantities
Import to order (with allowance)
—
Import tonnage
—
Import truckloads
—
Spoil to haul off (loose, with swell)
—
Spoil truckloads
—
How the Numbers Are Derived
The prism math
All volumes are the trench width × length × the relevant vertical slice, in bank (in-place) measure:
Excavation: W × D × L
Bedding: W × t_bed × L
Pipe zone: W × (OD + h_zone) × L − V_pipe, where the pipe displaces π/4 × (OD/12)² × L
Upper backfill: excavation − bedding slice − pipe zone slice
Conversion: 27 cf = 1 CY.
Bank vs. loose vs. compacted — the three cubic yards
The same dirt is three different volumes, and mixing them up is how orders go wrong:
Bank CY: in the ground, undisturbed — what the neat-line numbers are.
Loose CY: in the truck — bank × (1 + swell). This is what the hauling gets priced and scheduled on.
Compacted CY: back in the trench at spec density — for import, order more than neat-line because the loose delivered yard compacts smaller and some gets wasted. That's the compaction/waste allowance.
Spoil to haul: if native is reused above the pipe zone, the spoil is the material displaced by pipe + bedding + pipe-zone import (in bank measure), swelled. If everything above the pipe zone is also imported, the entire excavation hauls off.
Field notes
Depth varies along the run — for a long segment on grade, use the average of station depths, or split the run into reaches and run this per reach.
Trench boxes typically need 6–12 in. beyond their outside walls; if the box sets the dig width, use the box width plus over-cut, not the spec minimum.
Unsuitable subgrade at the bottom means over-excavation and extra bedding rock — a fast re-run of this tool with the deeper numbers is the change-order quantity backup.
Supplier tickets are in tons; inspectors think in CY; the trench is in bank measure. Keeping the three straight on the daily report saves the argument at the pay app.