Submittal & RFI Aging Tracker

Log open submittals and RFIs, see what's stuck in review as a days-in-review histogram, and track cycle times as items come back. Runs entirely offline; everything persists in this browser via localStorage.

Use limits: This is a field-side mirror, not the record. The submittal register in the project's PM platform (Procore, Kahua, e-Builder, ACC) is the contractual log. Age here is measured against the date sent — so it's only honest if you log each item the day it goes out, not from memory at the monthly meeting. Review durations and the definition of a “complete” submittal come from the contract specifications.
Settings

Typical spec review period is 30 days. Open items older than this are flagged.

Open & Closed Items
Ref / No.TitleTypeSentReturnedNoteAge / Cycle

Leave Returned blank while an item is open. A revise-and-resubmit comes back as a new line for the next revision (R0, R1…) so cycle times stay honest.

How the Numbers Are Derived

Aging, buckets, and the threshold

An item is open while its Returned field is blank. Its age is today − date sent in calendar days (dates parsed as local, so no timezone drift). Open items fall into buckets 0–7, 8–14, 15–30, 31–60, 60+ days — exactly 7 days lands in the first bucket, 8 in the second. A bucket is drawn in the fail tone when its entire range is past the threshold (its lower edge exceeds it); at the default 30-day threshold that's the 31–60 and 60+ buckets. Returned items leave the histogram but stay in the table with their cycle time (returned − sent) shown.

The stats panel

Median open age is the middle value of the open items' ages (average of the two middles for an even count). The oldest open item is your action item — name and age. “Over threshold” counts open items whose age exceeds the review duration. Average cycle time is the mean of returned − sent across every item that has come back — the honest measure of how long your reviews actually take, revision by revision.

Field notes

References

  1. Contract specifications — submittal procedures and review durations (Division 01, typically Section 01 33 00). Governing.
  2. The project's PM platform of record (Procore / Kahua / e-Builder / Autodesk Build) — the contractual submittal and RFI register. This page is a field-side mirror.