Scheduling arithmetic for forced-air ventilation of manholes, wet wells, and vaults: purge time from space volume, required air changes, and blower output derated for duct losses. Runs entirely offline; inputs persist in this browser via localStorage.
This tool does not clear a space for entry. Ever. Only calibrated atmospheric testing (oxygen, LEL, H₂S, CO at minimum — top, middle, and bottom of the space) by the qualified person, under the entry permit, clears a space — and continuous monitoring keeps it cleared. A calculated purge time tells you when it's worth testing again, nothing more. Sewer-connected spaces can re-contaminate in minutes from upstream slugs regardless of how long the blower ran. The permit, the attendant, the retrieval equipment, and the competent/qualified person requirements are all upstream of this arithmetic.
Results
Space volume
—
Effective airflow
—
Time per air change
—
Initial purge time ( changes)
—
After the purge: test the atmosphere per the permit before anyone enters, and keep the blower running continuously during occupancy — purging is a precondition for testing, not a substitute for it.
How the Numbers Are Derived
The math
t = V × N / Q_eff — volume (cf) times required air changes divided by effective delivered airflow (CFM), giving minutes. Effective airflow is the rated CFM times the duct-loss factor. That's the whole calculation; everything hard about confined spaces is in the parts that aren't math.
Placement matters as much as time
Duct the supply to within a couple of feet of the bottom of the space (or the far end of a horizontal one) so fresh air displaces from the bottom up. A blower parked at the rim churns the top and leaves the bottom — where H₂S sits, heavier than air — undisturbed.
Position the blower intake upwind and away from generator exhaust, truck exhaust, and the space's own vent discharge, or you're pumping CO in with great efficiency.
Sewer-connected structures: plug or block channels where the entry procedure allows, and expect the atmosphere to change when upstream flow changes — which is what the continuous monitor is for.
If the pre-entry test fails after a full calculated purge, the space has a supply problem (off-gassing, connected atmosphere), not a time problem — more minutes on the blower isn't the fix; the entry supervisor's re-evaluation is.
References
OSHA 29 CFR 1910.146 — Permit-Required Confined Spaces (general industry) and 29 CFR 1926 Subpart AA (construction). https://www.osha.gov/
The employer's written confined space program and the entry permit — governing procedures.
Blower manufacturer duct-loss data — actual delivered CFM for the duct setup in use.