Structure Buoyancy / Flotation Check

Factor of safety against flotation for an empty basin, wet well, tank, or vault with groundwater present — the check to run before draining a structure or turning off the dewatering. Runs entirely offline; inputs persist in this browser via localStorage.

Use limits: This is a screening check on the classic worst case — structure empty, groundwater high. It ignores side-wall friction and any structural anchorage (piles, tie-downs), which is conservative, but it also trusts your groundwater elevation, which is the input most likely to be wrong. If this tool says the FS is thin, the answer is the project geotech/structural engineer and the approved dewatering plan — not a slightly more optimistic groundwater guess.
Structure Geometry (outside dimensions)

The worst credible case: seasonal high, or the level when dewatering shuts off — not today's piezometer reading on a dry week.

Resisting Weight

If the cover soil is below groundwater, use the buoyant unit weight (total − 62.4).

Only count what is verifiably permanent and in place at the moment the structure is empty. Contents don't count — the check assumes empty.

From the project specs or the structural general notes — it varies.

How the Numbers Are Derived

The math

Uplift (Archimedes, in feet and pounds):

U = A_footprint × h_gw × 62.4

where h_gw is groundwater height above the bottom of the base slab, capped at the structure height. Resisting weight is concrete dead load (walls as the outside-minus-inside prism, plus base and top slabs at the footprint) plus soil cover plus any entered permanent weight:

FS = W_resist / U

The "max groundwater" line inverts this: the groundwater height at which FS drops to the required value — a useful trigger level for the dewatering plan ("keep the water below elevation X or the pumps stay on").

What this deliberately leaves out (and why)
Field scenarios where this bites

References

  1. ACI 350 — Code Requirements for Environmental Engineering Concrete Structures (flotation provisions and load factors). https://www.concrete.org/
  2. Project geotechnical report — design groundwater elevations (the governing input).
  3. Approved dewatering plan — the document this check should send you back to when the FS is thin.