Basin Hydrostatic Test Calculator

Water-tightness (liquid loss) testing of concrete basins, tanks, and channels per the ACI 350.1 method: corrected water surface drop against the allowable percentage of volume per 24 hours. Runs entirely offline; inputs persist in this browser via localStorage.

Use limits: This computes the arithmetic of the test. The governing acceptance criterion (0.05% vs. 0.10% of volume per 24 hr, or something project-specific), the stabilization period, the test duration, and what happens on a failure all come from the contract specs and the referenced edition of ACI 350.1. Fill rates, temporary bulkheads, and disposal of test water are their own plan.
Basin Geometry at Test Water Level

Test water level should be at the maximum operating level unless the spec says otherwise.

Test Measurements

From fixed reference gauges/points, not the same wet mark eyeballed twice.

A calibrated open pan floating in the basin sees the same evaporation and rainfall as the basin. Net leakage drop = basin drop − pan change.

Acceptance Criterion

The designation is on the drawings or in the specs — 0.05% is typical for environmental structures.

How the Numbers Are Derived

The math

Corrected leakage drop:

Pan method: Δh = drop_basin − Δh_pan (the pan sees the same evaporation and rainfall, so subtracting it isolates leakage).
Split method: Δh = drop_basin − evaporation + rainfall.

Volume lost: V_lost = Δh/12 × A × 7.48 gal. Loss rate normalized to 24 hr:

%/24hr = V_lost / V_test × (24 / t_hr) × 100

The pre-test planning number — the allowable drop in inches over your test duration:

Δh_allow = (allow%/100) × V_test / (A × 7.48) × 12 × (t_hr/24)

Running the test so the numbers mean something

References

  1. ACI 350.1 — Specification for Tightness Testing of Environmental Engineering Concrete Containment Structures. https://www.concrete.org/
  2. AWWA D110 / D115 — tightness testing provisions for circular prestressed tanks, where applicable.
  3. Contract specifications — governing criterion, stabilization period, and retest provisions.